Encinitas ADU rules and permits, step by step
Encinitas publishes its ADU process in more detail than most cities. That helps, but the process runs through several departments, and two outside agencies, before you can build. Here's the sequence as the city describes it, plus the points where projects tend to stall.

ADU or JADU?
An ADU is an attached or detached home with its own kitchen, bathroom and sleeping space, on a lot with an existing single-family, multifamily or mixed-use building. A junior ADU (JADU) is no more than 500 sq ft, sits entirely inside a single-family home (existing or planned), and has an efficiency kitchen. A JADU can share a bathroom with the main house. JADUs aren't allowed in multifamily buildings.
Which rules apply
The local rules are in Encinitas Municipal Code section 30.48.040.T. State ADU law was moved to new Government Code sections (66314 through 66339) in 2024, and the city's own ADU and JADU guide cites both. The city started updating its code for that change in September 2024. We haven't found a record that the update was adopted, so where the city code and current state law differ, state law controls. The state's rules are summarized in the HCD ADU Handbook, updated March 2026.
The eight steps
- Talk to the city first. The city recommends consulting staff before or while you draw plans. That means Planning, Land Development Engineering, Building, Fire Prevention, and your water district, which is either San Dieguito Water District or Olivenhain Municipal Water District. Planning handles steep slopes, coastal bluffs, height limits and coastal permits. Engineering handles grading, drainage and stormwater.
- Assemble the submittal. You'll need full project plans (site, floor, elevations, roof, structural, electrical, plumbing). You'll also need a grading plan if one applies, the Stormwater Intake Form and the Housing Development Tracking Form. Add the current grant deed, a preliminary title report no more than six months old, and a geotechnical report if the new construction or addition is 500 sq ft or more.
- Submit online. Applications go through the city's Customer Self-Service (CSS) portal. After intake, the city emails the water, sewer and school fee forms. You take those to each agency, pay their fees, and upload the signed forms before the permit can be issued.
- Review. Building, Land Development, Fire Prevention and Engineering review the plans together. The city puts each round at about 15 working days, and redlines come back once every reviewer has finished.
- Coastal Development Permit, if your lot is in the Coastal Zone. See the next section.
- Resubmit. Answer each division's comments and upload revisions. Along the way the city sends an ADU covenant, which the owner signs in front of a notary and returns as a wet-signed original for recording.
- Permit issued. The permit is issued after every division signs off and all outside forms are in: contractor or owner-builder form, water, sewer, school fees, waste management plan and SDG&E work order. The city's advice is to start on the outside agencies early.
- Build and inspect. Inspections are booked in the CSS portal. If they're booked by 3 p.m. on a business day, they happen the next business day. If the reviewer requires a height certification, the surveyed heights must be approved before the roof-nailing inspection.
When you need a Coastal Development Permit
Much of Encinitas is in the Coastal Zone. There, an ADU or JADU needs a Coastal Development Permit (CDP) unless it is completely contained in the existing main house. It also needs one if it adds habitable area, converts non-habitable space such as a garage, or is a detached unit. That wording comes from a 2022 change the Coastal Commission required in the city's code.
The CDP runs alongside your building permit:
- The planner reviewing your building permit opens a separate CDP record and asks for a reduced plan set, the grant deed and the title report.
- You print the notice sign the city sends, post it on the property where the public can see it, and upload a photo with the certificate of posting.
- You pay a postage fee, the city mails a legal notice, and there's a 10-day comment period.
- The Director signs a Notice of Decision. You then sign an indemnification agreement in front of a notary and return the original.
- If the lot is in the Coastal Commission's appeal jurisdiction, a 10-business-day appeal period starts once the Commission receives the city's Notice of Final Action.
The building permit can't be issued until the CDP is.
Fees
Encinitas waives its own plan review and inspection fees for ADUs. You still pay required state fees, County Recorder fees for the covenant, and postage if you need a coastal permit. Water, sewer and school fees are charged separately by those agencies.
Using a preapproved plan
A city-preapproved plan still follows these steps. It needs a site plan, and it may need grading review and a coastal permit. You also can't change the drawings. See our comparison of all eight Encinitas preapproved plans.
Unpermitted ADUs
Under Government Code 66311.7, the city can't deny a permit to legalize an ADU or JADU built before January 1, 2020, unless fixing a violation is needed to correct a substandard condition. The Coastal Act still applies. The city publishes a separate legalization guide and checklist.
Which page answers your question?
| Question | Guide |
|---|---|
| How big and tall? | Setbacks, height and size |
| Do I need parking? | ADU parking |
| Sloped or bluff lot? | Hillside and bluff lots |
| Fees? | ADU cost |
| Garage? | Garage conversions |
Everything the city checks
- One ADU plus a JADU per single-family lot
- Size and height
- Setbacks and overlays
- Parking or exemption
- Separate entrance
- Energy and solar
- Utilities and septic
- Fire
- Covenant
- Coastal permit
Sources, all checked Oct 14, 2026: City of Encinitas ADU page · City ADU and JADU guide · Council agenda report, Resolution 2024-110 · Coastal Commission staff report, July 2022 · HCD ADU Handbook.
Questions we hear
Can I have an ADU and a JADU in Encinitas?
Yes. EMC allows an ADU on a lot with a JADU.
What are the new ADU laws in California for 2026?
State law keeps changing. Encinitas's ADU code cites state law as controlling where it conflicts, and the city initiated updates for recent bills. We check the current EMC and city guidance for each project.