Junior ADUs in Encinitas

A junior accessory dwelling unit is a small unit created inside your house. Encinitas regulates JADUs in EMC 30.48.040 subsection U, and the rules make them the lowest-cost unit to add: no parking, no impact fees, no sewer or water connection fees, and, when nothing is added to the house, no coastal permit.

JADU standards

StandardRequirement
NumberOne per single-family residence, on lots zoned single-family or multifamily
LocationEntirely within the walls of a proposed or existing single-family residence
Size500 sq ft of total floor area maximum
EntrySeparate exterior entry
KitchenEfficiency kitchen: a cooking facility with appliances, plus a food prep counter and storage cabinets sized to the unit
BathroomIn the JADU, or in the house with direct interior access
ParkingNone
SprinklersNot required unless required for the house
FeesNo impact fees; no sewer or water connection fees
RentalOnly for terms greater than 30 days
OwnershipCan't be sold separately; owner occupancy required
ApprovalMinisterial, decided within 60 calendar days of a complete application
Worker in a Encinitas ADU Builders vest leveling kitchen base cabinets in an ADU while a coworker sorts hardware at a table
Kitchen cabinet installation, in the field.

The covenant

Before the building permit is issued, the owner records a covenant with the city. It states that the JADU won't be sold separately, will be rented only for terms over 30 days, is limited to the size and features in the code, and that the owner of record lives in the house, the JADU or the ADU. It binds future owners. The city emails the covenant during review, and it must be signed, notarized and returned as a wet-signed original.

Shared or private bathroom

Encinitas lets a JADU rely on a bathroom in the main house, but only with direct access from the JADU to the main living area. If the household wants the JADU fully separate, for example as a rental, it needs its own bathroom. That's usually the biggest cost decision in a JADU.

Adding a JADU and an ADU

A JADU can be built in a house on a lot that also has an ADU. The owner can then live in any of the three units. A detached ADU plus a JADU is a common combination for multigenerational households.

In the Coastal Zone

A JADU that's completely contained in the existing house, adds no habitable area and doesn't convert non-habitable space (such as a garage) is a self-contained unit and doesn't need a Coastal Development Permit. Converting an attached garage, or adding space, does trigger one. See the coastal permit steps.

Exempt from street improvements

JADUs are exempt from requirements to underground overhead utilities and to dedicate or improve the public right-of-way.

JADU or ADU in Encinitas

JADUADU
WhereWithin the walls of a single-family homeAttached, detached, above garage, conversion
Size500 sq ft total floor areaUp to 1,200 sq ft
KitchenEfficiency kitchenFull kitchen
ParkingNoneOne space unless exempt
Owner occupancyRequired (covenant)Not required
Connection feesNoneProportional, none for conversions
Impact feesNoneNone under 750 sq ft
Coastal permitNone if contained in existing spaceDepends on type
Multifamily lotsNot allowedAllowed

Sources: EMC 30.48.040.T and U; city ADU page.

Step by step

  1. Consult staff (optional, recommended): Planning, Land Development Engineering, Building, Fire Prevention, and your water district.
  2. Assemble the submittal: project plans, grading plan if applicable, Stormwater Intake Form, Housing Development Tracking Form, grant deed, preliminary title report (6 months or newer), and a geotechnical report for new construction or additions of 500 sq ft or more.
  3. Submit in the CSS portal. Technicians check completeness and email the water, sewer and school fee forms.
  4. Review by Building, Planning, Fire Prevention and Engineering, about 15 working days per round.
  5. Covenant: sign, notarize and return the ADU covenant; pay County Recorder fees in CSS.
  6. Issuance once all divisions approve and agency forms, contractor or owner-builder form, waste management plan and SDG&E work order are in.
  7. Inspections scheduled in CSS; requests by 3 p.m. are done the next business day. Height certification before roof nailing if Planning requires it.

Checklist

How Encinitas homeowners use JADUs

UseWhy it fitsWatch for
Family member nearbyShares the house; bath can be shared via interior accessOwner-occupancy covenant
Long-term rentalNo parking, no impact or connection feesRentals over 30 days only
Coastal Zone lotsNo CDP when fully within existing spaceAdding area or converting non-habitable space triggers a CDP
JADU plus an ADUEMC allows an ADU on a lot with a JADUOwner lives in the house, JADU or ADU

Sources: EMC 30.48.040.T and U; city ADU page.

Common JADU mistakes

Sources, checked Oct 14, 2026: EMC 30.48.040 · City of Encinitas ADU page.

Questions we hear

Does a JADU need a coastal permit in Encinitas?

Not if it is completely contained within the existing house, adds no habitable area and doesn't convert non-habitable space. Otherwise, in the Coastal Zone, it needs a Coastal Development Permit.

Who has to live on the property with a JADU?

The owner must live in the main house, the JADU, or the ADU if there is one, unless the property is held by a government agency, land trust or housing organization creating affordable housing. This is recorded in a covenant.

Can a JADU share a bathroom with the house?

Yes. If the bathroom is in the main house, the JADU must have direct interior access to the main living area so the occupant doesn't have to go outside to reach it.

What is a Jr. ADU in California?

A small unit inside a single-family home. In Encinitas it's up to 500 sq ft, with an efficiency kitchen and its own exterior entry, and the owner must live on the property.

What's the cheapest way to add a unit in Encinitas?

Often a JADU in existing space: no parking, no impact or connection fees, waived plan review fees, and no coastal permit if it's fully contained.

What are the downsides of a JADU?

It's capped at 500 sq ft with an efficiency kitchen, needs owner occupancy, and can't be sold separately or rented for 30 days or less.