Answering Plan Check Comments on an Encinitas ADU
Encinitas sends every ADU to four reviewing divisions, and comments come back as notes in the portal, redlines or both. State law now sets clear rules for completeness and denial comments. A tidy, comment-by-comment response does the rest.
Published Nov 18, 2026
Plan check comments aren't a verdict. They're a to-do list written by several reviewers at once, and on almost every ADU there's at least one round. The owners who move fastest through Encinitas review aren't the ones with perfect first submittals. They're the ones who answer every comment clearly, in one organized package, and ask questions before resubmitting instead of after.
How the first review is set up
The City of Encinitas lays out its ADU process on its ADU page. Applications go in through the Customer Self Service portal, CSS. Building technicians check the submittal for completeness and then route it to four divisions: Building, Land Development & Building, Fire Prevention, and Land Development Engineering. The City describes the review time as approximately 15 working days, which is a description of the process, not a promise for your project.
Each division comments on its own. Comments may appear in CSS, as redlines on the plans, or both, and the City notes that redlined plans become available once all division reviewers have finished. That detail matters. A comment from one division can show up before another division's redlines are posted, so wait for the full set before you start revising sheets.
What state law adds
Government Code Section 66317, amended by SB 543 effective January 1, 2026, sets a few ground rules for every ADU application in California:
- The agency has to tell you in writing whether the application is complete within 15 business days of receiving it.
- If it's incomplete, the agency must list the missing items and explain how to complete them.
- When you resubmit to cure those items, the agency can't add new items that weren't on the list.
- If the agency misses the completeness deadline, the application is deemed complete.
- Once an application is complete, the agency has 60 days to approve or deny it when there's an existing home on the lot.
- A denial has to come with a full set of written comments listing what's deficient and how to fix it.
- Agencies must offer a written appeal process, with a final decision within 60 business days of the appeal.
HCD's March 2026 ADU Handbook explains that a full set of comments means all comments from all reviewers, from every permitting agency involved. It also says a subsequent application after a denial starts a new 60-day period, and that an agency may charge a fee to process a resubmitted application.
None of this makes corrections disappear. Building code, health and safety and fire items still have to be met. What the law does is make the comment list predictable, and that helps you plan the response.
Read the whole set before touching a sheet
Start by pulling every comment into one list, by division and by sheet. Give each one a number. Note which comments depend on each other. A fire separation comment, for example, can change a wall assembly that the energy documents and structural details also rely on. Encinitas lists fire separation and setbacks among its common building topics, so those are worth reading closely on a lot where the ADU sits near a property line.
Then sort the comments into three groups:
- Clear fixes. Missing dimensions, a detail reference, a note on a sheet.
- Design changes. Items that move a wall, change a window or alter grading.
- Questions. Comments you don't fully understand or think may not apply.
Ask before you resubmit
The City's own advice is direct. Before resubmitting, direct questions about corrections to the individual reviewer for that division, which the City says may reduce the number of reviews and the time to a permit. A short, specific question, with the comment number and sheet, gets a better answer than a general one. Keep the reply with your response package.
Build the response package
A good response has two parts: the revised plans and a written comment-by-comment reply.
For the reply, repeat each comment, then state what changed and where. "Comment 7, Building: added one-hour wall rating and detail 4 on sheet A3.1" is the right level. If you believe a comment doesn't apply, say why, politely, and cite the plan location or code section you're relying on.
For the plans, mark changes so reviewers can find them. Encinitas uses a related convention on its form for revisions to approved plans, BLD-100: clouded changes, a revision number such as REV1 with a date on every affected sheet, and a narrative listing revisions sheet by sheet. That form is for changes after a permit is issued, not for plan check responses, but the same habits make a resubmittal easy to review. If an architect or engineer prepared the original sheets, have that person revise and sign their sheets.
Resubmit through the right door
The City's CSS guides separate two tasks that are easy to confuse. "How to Resubmit Your Files" covers uploading after a failed review, which is what a plan check response is. "How to Submit a Revision" covers changes after the permit has been issued. Use the resubmittal path for comment responses, and use the status guide to watch where each division stands.
Paperwork that runs alongside review
Some items move on their own track while plans are in review. During review, the City emails an ADU covenant that must be signed and notarized by the owner, with the original wet-signed document returned. Water, sewer and school forms come from the building technicians after submittal and must be signed by those agencies and uploaded before issuance. In the Coastal Zone, the coastal development permit process runs in parallel, and the City says the building permit can't issue until the coastal permit is issued and all corrections are addressed.
When you disagree
If an application is denied and you think the denial is wrong, the appeal process required by Section 66317 is the formal path. HCD offers technical assistance through its ADU Portal, but the handbook asks applicants to work with the local agency first, and HCD may not follow up if there's no pending application. A calm, documented response almost always gets further than escalation. Keep every comment list, reply, email and resubmittal date in one folder, because that record is what any appeal or technical assistance request will rely on.
Our plan check page and permits page cover the Encinitas review path in more detail, and our post on owner-builder ADU risks covers who should be signing what.
We work with verified contractors who prepare clear, comment-by-comment responses for Encinitas ADU plan check and coordinate with the designers who drew the plans. If you're facing a stack of redlines, request a Free Quote consultation.
Sources (accessed Nov 18, 2026): Accessory Dwelling Units (City of Encinitas, Development Services) · CSS Guides (City of Encinitas) · Revisions/Deferred Submittal to Approved Plans (BLD-100, Aug. 2023) (City of Encinitas, Development Services) · Government Code Section 66317 (California Legislature) · Accessory Dwelling Unit Handbook (March 2026) (California Department of Housing and Community Development)