Soils Reports for Encinitas ADUs: Report or Waiver
The City's ADU application lists a geotechnical letter report for most new units, and it also lists the kinds of existing records that can stand in for one. Here's how the report-or-waiver question plays out, and what the engineer is actually looking for.
Published Nov 24, 2026
Encinitas lots range from flat graded pads to hillsides and bluff-top parcels, and two lots on the same street can behave very differently under a new foundation. That's why the City's ADU application includes a soils item. For a lot of owners, the first real question is whether it applies to them, and if so, whether something they already have can satisfy it.
The line on the City's list
The City's ADU and PRADU permit application lists a geotechnical letter report among the required documents. The wording is specific: it applies if the building is over 500 square feet, unless the Building Official waives it. The PRADU submittal checklist repeats the same line under its engineering items.
A geotechnical letter report is a shorter document than a full geotechnical investigation. A geotechnical engineer looks at the site and gives the designer what's needed to size the foundation. The checklist doesn't spell out its contents, so the engineer and the reviewer settle the scope.
Under 500 square feet, the line doesn't apply on its face. That doesn't mean a small unit can never be asked for soils information. Under the residential code, the building official still decides whether a soil test is needed when there's reason to suspect questionable soils.
The City's own waiver examples
The application doesn't just say "unless waived." It gives examples of when a waiver might fit:
- The ADU sits on a certified pad. On lots graded as part of a subdivision, the pad may have been certified by an engineer when it was built.
- There's a compaction report for the pad. If fill was placed and tested, that report may still describe what's under the site.
- The City already has a soils report on file. An earlier project on the property may have produced one.
The application closes the list with "others subject to Building Official's review," so the examples aren't the only path. Whether any of them works on your lot is the Building Official's call.
Turning the waiver into a records search
Those examples point to a practical first step: look for existing paperwork before ordering new work.
- Ask the City for the property's permit history. Past permits for additions, pools or retaining walls may have come with soils reports.
- Check your closing documents. Grading certifications and soils reports sometimes travel with the purchase file on newer subdivisions.
- Ask the original builder or HOA. On tract homes, the subdivision's grading reports may cover your pad.
- Note the date and scope. An old report written for a different structure in a different spot on the lot may not answer the questions for a new ADU.
If the paperwork exists and covers the area where the ADU will go, it can support a waiver request. If it doesn't, you'll know early that a letter report belongs in the schedule.
Keep copies of whatever you find with the rest of your permit file. If the Building Official accepts an existing report, the plan reviewer and the inspector may both want to see it, and the designer will need the numbers in it to size the footings. A waiver request is stronger when it's specific: which report, what date, which part of the lot it covered and why it applies to the new unit.
Why the code lets a reviewer skip it
The waiver isn't a City invention. Section 1803.2 of the 2025 California Building Code lets the building official waive a geotechnical investigation where satisfactory data from adjacent areas show it isn't necessary. The residential code works the other way around. Under Section R401.4, the building official decides whether to require a soil test where data from accepted soil science methods indicate expansive, compressible, shifting or other questionable soils are likely.
Where no test is required, Section R401.4.1 lets the designer use presumptive values from the code's tables. Those tables assume conservative bearing values by soil class and flag high-plasticity clays and silts as having high expansion potential. A footnote says that where the building official expects soils weaker than the lowest table value, bearing capacity has to come from a soils investigation.
Slopes, fill and overlays
Some Encinitas lots carry extra review that touches soils even when the letter report is waived. The PRADU checklist asks for existing and proposed contours at intervals of no more than two feet, an average lot slope exhibit, and, where grading is involved, earthwork quantities with the maximum depth of cut and height of fill. If the property is in the Special Study Overlay Zone or the Hillside/Inland Bluff Overlay Zone, the checklist says to contact the Planning Division to find out whether a slope analysis is required.
The residential code adds that fill soils supporting footings have to be designed, installed and tested according to accepted engineering practice. A pad that was built up without testing is a common reason a reviewer wants a fresh look. Our hillside and bluff ADU page covers the overlay side in more depth.
What a report tells your designer
When a full investigation is required, the building code lists what the written report should contain. It includes a plot of where the soil was explored, boring or test pit logs, the soil profile and the water table if one was found. The report then gives recommendations on foundation type and design criteria. Those cover bearing capacity, how to deal with expansive soils, and how to limit the effects of liquefaction and differential settlement. It also covers expected settlement and the properties and testing of any compacted fill.
Those recommendations feed straight into the structural drawings. They can decide whether a slab works, how deep footings go and whether the pad needs to be over-excavated and recompacted. Our post on choosing a slab or raised foundation picks up from there.
Timing it right
A soils letter is easiest to handle early. If it comes in after the structural design is drawn, the design may need to change, which means another round of plan check. Ordering it, or confirming the waiver, before the engineer sizes the foundation keeps the drawings and the report in step.
It also helps to share the site plan with the geotechnical engineer before the site visit. Knowing exactly where the ADU will sit, how big it is and whether it's one or two stories lets the engineer put test pits or borings where they're actually useful. A report that explores the wrong corner of the lot can leave the reviewer with the same questions.
How we help
We work with verified contractors and design teams who build ADUs across Encinitas, and we coordinate with licensed engineers as needed on soils and foundation questions. Ask for a Free Quote. Our ADU permits and plan check guides cover the rest of the submittal, and our detached ADU page covers the build.
Sources (accessed Nov 24, 2026): Accessory Dwelling Unit (ADU) or Permit-Ready Accessory Dwelling Unit (PRADU) Permit Application (City of Encinitas Development Services) · PRADU Submittal Checklist (City of Encinitas Development Services) · 2025 California Residential Code, Section R401 (California Building Standards Commission (via GoCodebook)) · 2025 California Building Code, Section 1803 Geotechnical Investigations (California Building Standards Commission (via GoCodebook))